More accessibility and comfort for Tscherttegasse U6 station
New lift and better accessibility, more space and comfort
Wiener Linien has installed a new lift, meaning both platforms are now accessible to all. The platform towards Floridsdorf has been widened in places to more than four metres. In addition, both platform roofs have been extended by 35 metres each – so you are protected from bad weather or strong sunlight along almost the entire length. The new ground-level access to the adjacent park ensures a comfortable journey to and from the station.
By autumn 2026, a bridge will be built over the tracks, creating an additional link between the platforms. And in the middle of the platforms, a further access point to Miep-Gies-Park will be created, improving connections to the Kabelwerk residential area and shortening the distances when boarding and alighting.
Construction work schedule
| From April 2025 ✅ | Lift shaft and platform track 1 |
|---|---|
| From June 2025 ✅ | Foundation and barrier-free access to track 1 |
| From September 2025 ✅ | Foundation and barrier-free access to track 2 |
| From February 2026 ✅ | Extension of platform roof on track 2 |
| Summer/autumn 2026 | End of construction |
Wiener Linien Customer Service
-
Do you have questions about your ticket? Have you been found without a valid ticket and have to pay an additional fee? Do you have questions or problems when buying tickets online? Whatever concern you have: We are happy to take care of it!
Get in touch with us
-
Handle your request online: Visit our Help Center
-
Find an office: Offices & opening hours
-
Call our customer hotline: +43 1 7909 100
2025-ZOOMVP_1180.jpg)